Construction Is Heating Up This Summer at Kenowa Hills

  • Writer: Owen-Ames-Kimball  Co.
    Owen-Ames-Kimball Co.
  • Jul 1
  • 3 min read

Summer construction is in full swing across Kenowa Hills Public Schools as crews make progress on Phase 2 athletic improvements while beginning work on the next phase of renovations at the Early Childhood Center (ECC). These projects are designed to enhance both athletic facilities and learning environments, ensuring students have access to modern, functional spaces for years to come. Let's take a look at what's happening on our construction sites this summer!


The new Kenowa Hills team Room is making great progress this summer! It is expected to be complete for the fall 2026 athletics season.
The new Kenowa Hills team Room is making great progress this summer! It is expected to be complete for the fall 2026 athletics season.

Phase 2 Athletics: Ready for Football Season

Construction on the district's Phase 2 athletic improvements continues to move forward, with major components on track to be completed in time for the upcoming football season. Here's a look at the progress:


New Field Events Area

Work has begun on the new field events area for our track and field athletes. This space will include dedicated areas for discus and shot put. Concrete placement is about to begin, marking an exciting milestone as this new competition venue starts to take shape.


Visitor Team Building

The new visitor team building is making great progress. Structural bearing walls and the roof framework have been completed, with roofing installation scheduled next. Inside the building, plumbing rough-ins are underway while masonry crews continue constructing the interior walls. When complete, the facility will include a large visitor team room and new restroom facilities, creating a more modern and functional space for our visiting teams.


Visitor Bleachers

Installation of the new visitor bleachers is approximately 90% complete. The remaining work includes installing the stairs and accessibility ramps before the area is ready for use this fall.

Pictured above: visitors team room and bleachers


Home Team Building

Significant interior progress has also been made inside the new home team facility.

Current work includes:

  • Exterior concrete preparations

  • Locker installation underway

  • Restroom plumbing rough-ins completed

  • Coaches' offices painted and ready for ceiling installation

  • Athletic training room painted and prepared for ceilings

The existing team room building will be repurposed to support the district's junior varsity athletic teams.

Pictured above: new team room addition


Multipurpose Turf Field

Work continues on the district's new multipurpose turf field, which will serve football, soccer, lacrosse, PE classes, and more! Located north of the stadium, the site has been graded and is ready for fencing installation. Crews will soon install the concrete perimeter needed to support the fence system. Once complete, the field will be prepared for turf installation before the final playing surface and sport-specific field markings are added.

Pictured above: the future site of the multipurpose field, getting ready for turf.


Early Childhood Center Phase 2 Begins

Construction has officially begun on Phase 2 of the Early Childhood Center improvements, building upon the successful first phase completed previously.

Crews are currently completing abatement work on a portion of the existing building in preparation for demolition and the construction of a new addition. Abatement is expected to wrap up by the end of the week, after which demolition will continue on the designated section of the facility. As part of this phase, a portion of the building will be completely removed and rebuilt, while four classrooms will be renovated to better serve students and staff. To support the new addition, crews are also expanding the site's stormwater retention pond, with excavation expected to be completed this week.

Pictured above: these wings of the current ECC will be completely removed and the addition will be placed. The drive space pictured will become a new playground.


Renovated Learning Spaces

Four existing classrooms will be transformed into new support spaces, including:

  • A new kitchen

  • Office space and a teacher lounge

  • Mechanical and IT support space

  • A motor room


The renovated Extended Learning Areas will mirror the finishes and layout completed during Phase 1, creating a cohesive learning environment throughout the building.


Check out these photos from the previously completed areas of the ECC. Phase 2 could look something like this!


New Playground & Gymnasium Renovation

Students will also benefit from a brand-new playground as part of the Early Childhood Center improvements. The updated outdoor play area will provide expanded opportunities for recreation and learning while complementing the renovated facility.

Renovations to the ECC gymnasium are also a part of this phase.


Phase 2 of the Early Childhood Center project is anticipated to be completed in summer/fall 2027.


As construction continues across the district, Kenowa Hills Public Schools remains committed to creating modern learning environments and athletic facilities that will serve students, staff and the community for generations to come. Be sure to check back for future bond updates as these exciting projects continue to progress.

 
 
 
GMB Logo.png

ARCHITECTUrAL PARTNER

GMB is a full service A/E firm, and serves as the architectural partner Rockford Public Schools

SUBSCRIBE VIA EMAIL

O-A-K Logo, Website Navy, Square.png

BROUGHT TO YOU BY O-A-K

Owen-Ames-Kimball Co. is our construction management partner for all construction projects.